Poland’s GDDKiA promises to improve road procurement processes

The Polish national roads authority GDDKiA has said that it will no longer look for the cheapest offer in road-building tenders. Instead, it will, in line with European Union requirements, consider whole life cycle factors such as durability, cost of exploitation and quality. Poland has long been criticised by the road construction industry, both within the country and in the rest of Europe, for handing out tender wins to the lowest bidder with scant regard for life-cycle costs. The government has also b
January 12, 2015 Read time: 2 mins
The Polish national roads authority 1361 GDDKiA has said that it will no longer look for the cheapest offer in road-building tenders. Instead, it will, in line with 1116 European Union requirements, consider whole life cycle factors such as durability, cost of exploitation and quality.

Poland has long been criticised by the road construction industry, both within the country and in the rest of Europe, for handing out tender wins to the lowest bidder with scant regard for life-cycle costs. The government has also been heavily criticised for refusing to negotiate with winning contractors when unforeseen issue push up construction costs.

3260 World Highways %$Linker: 2 Internal <?xml version="1.0" encoding="utf-16"?><dictionary /> 2 2988 0 oLinkExternal reported in mid 2011 Visit WH Story Page false /sections/general/news/polish-project-causes-further-legal-headaches/ false false%> that Chinese contractor China Overseas Engineering Group Co (2487 COVEC) had appealed against a decision made by GDDKiA to cancel the contract that Covec had to build a section of the A2 highway between Warsaw and Lodz. Covec's tender win was a landmark decision, the first time a Chinese firm had won a major construction contract in Europe. The firm won the tender process for the 50km highway with a bid so low that it caused some bidders to complain about undercutting.

Covec’s problems started soon after work started when material prices spiralled upwards. Delays mounted as did complaints from local sub-contractors over non-payment by the main contractor. Covec withdrew from the project in May 2011.

Despite the GDDKiA announcement that it plans to adhere to EU procurement law, the government agency remains besieged by construction firms locked in legal battles over how they have been treated. According to one news agency, the companies claim billions of euros are owed to them by Poland. Polish contractors have said some of them have gone to the wall because of lack of payment by the government. Six European governments have complained to Poland about the treatment meted out to private companies.

The GDDKiA’s also said its Podlaskie regional unit will spend around $228 million on road projects in 2015, up from $166 million last year. Among projects earmarked for completion are ring roads around Szczuczyn and Barglow, as well as the S8 section between the ring road of Zambrow and Mezenin.

For more information on companies in this article

Related Content

  • Funding problems for major Polish highway project
    May 9, 2012
    The long tale of woe concerning Poland’s troubled A2 highway project looks set to continue with the latest developments in the case. The Chinese contractor China Overseas Engineering Group Co (Covec) is appealing against a decision made by the Polish national road authority GDDKiA. The Polish authorities cancelled the contract that COVEC had previously been awarded to build a section of the A2 highway between Warsaw and Lodz.
  • Polish project causes further legal headaches
    February 28, 2012
    The long tale of woe concerning Poland's troubled A2 highway project looks set to continue with the latest developments in the case.
  • Budimex consortium win Poland’s Ostroda ringroad court case
    March 18, 2015
    A district court in the Polish town of Olsztyn has ruled in favour of a consortium of Budimex and Ferrovial Agroman which challenged the awarding of a ringroad contract to a rival. The ruling means that the Salini consortium’s winning bid for the construction of a ringroad around Ostroda is overturned on the basis that it was ineffectually low. This means that the contract will go to the Budimex consortium which proposed to build the road for around €223 million. Polish builder Budimex is the consortium's m
  • Polish road dispute
    February 28, 2012
    A string of legal and political battles look likely in the aftermath of a broken highway contract in Poland.