DEMOLITION and blasting experts Philipp Halter of Berlin, Germany, faced a challenging job: in just 48 hours it had to demolish the southern section of the Spandau Dam Bridge crossing the A 100. The efficient interaction of Atlas Copco hydraulic breakers and hydraulic CombiCutters, mounted on seven Volvo excavators, is said to have played a crucial role after following a carefully planned schedule. During Friday night a bed of sand was placed under the bridge to allow the girders and reinforcements torn dow
March 2, 2012 Read time: 2 mins
DEMOLITION and blasting experts 1215 Philipp Halter of Berlin, Germany, faced a challenging job: in just 48 hours it had to demolish the southern section of the Spandau Dam Bridge crossing the A 100.

The efficient interaction of 161 Atlas Copco hydraulic breakers and hydraulic CombiCutters, mounted on seven 2394 Volvo excavators, is said to have played a crucial role after following a carefully planned schedule. During Friday night a bed of sand was placed under the bridge to allow the girders and reinforcements torn down by the Atlas Copco CombiCutters to be safely collected
and transported.
 
Three 283 MB 1700 hydraulic breakers (each weighing 1,700kg and suitable for carriers in the 19-32tonne weight class) began with preparations on the bridge foundations. An SB 302 was used for the less demanding preparatory and finishing work, such as in narrow places. The light hydraulic breaker weighs 304kg and is suitable for carriers in the 4.5-9tonne weight class.

The main part of the work was handled by two Atlas Copco hydraulic CombiCutters (a CC 1700 U and a CC 2500 U) equipped with 'Universal' jaws, which crushed the concrete and cut the strong rebar of the bridge in one go. The cutters weigh 1,680kg and 2640kg, respectively. The roadblocks were removed at 5am on Monday, according to schedule, making way for one of the most significant roadwork projects in the capital on the banks of the River Spree.

For more information on companies in this article

Related Content

  • Atlas Copco for Brazil bridge demolition
    July 2, 2013
    Brazilian demolition specialist Comprex was chosen to demolish a bridge connecting districts in the city of Vitória in the state of Espirito Santo. For environmental reasons, debris was not permitted to fall into the waterway under the bridge, and special arrangements had to be made for the removal of the demolition waste. Comprex chose Atlas Copco hydraulic breakers and CombiCutters for the jobsite where three new bridges have been built over the old bridge, which was no longer able to support the increasi
  • 48 hours re-opening
    July 6, 2012
    Using demolition tools from Atlas Copco helped to maximise productivity on a highly time-sensitive project in Germany. The A3 autobahn runs from the Dutch/German border through the western part of the Ruhr area, the Cologne area, the Rhine-Main area and Bavaria down to the Austrian border at Stuben. It is one of the most heavily used highways in Germany and because of increasing traffic volumes, widening the road to six lanes has become necessary.
  • High speed bridge demolition minimises disruption
    April 13, 2012
    A high speed bridge demolition project has been carried out successfully in Germany. Speed was of the essence as the bridge spanned an important road link and had to be removed in a tight time frame, minimising disruption to traffic.
  • High speed bridge demolition minimises disruption
    February 16, 2012
    A high speed bridge demolition project has been carried out successfully in Germany. Speed was of the essence as the bridge spanned an important road link and had to be removed in a tight time frame, minimising disruption to traffic.