Skip to main content

Businesses want Crnaja Tunnel delay

The tunnel is on Bosnia’s M17 highway, part of European route E73.
By David Arminas September 25, 2020 Read time: 1 min
Time on their hands: delays could be in store for work on Bosnia’s Crnaja Tunnel (photo © Piotr290/Dreamstime)

A major business association in Bosnia wants renovation work on the Crnaja Tunnel to be delayed until better bypass routes can be planned.

In a letter to the government, the Union of Business of Federal Bosnia and Herzegovina said work on the two-lane tunnel would greatly disrupt truck transport along on the Jablanica-Konjic segment of the M-17 highway. Now, during a time when many businesses are suffering financial loss due to the COVID pandemic, is not the time to further hamper any economic recovery.

The M17 is part of European route E73 and runs from northern Croatian border in Šamac towards southern Croatian border near Čapljina.

A €6.5 million contract for reconstruction of the road section and tunnel was announced in June last year and is being funded by the International Bank for Reconstruction and Development as well as the European Investment Bank.

The project has run into poor soil conditions and road transport is often severely disrupted because few alternative routes exist for heavy goods vehicles, noted a report by the Bosnian national news agency FENA.

Related Content

  • Bosnia gets EBRD loan for Corridor 5c work
    January 8, 2024
    The project will include the construction of an interchange and a 15 km dual-carriage motorway section, along the Mostar North-South section.
  • Bosnia cancels a tender for Corridor 5C, part of European route E73
    March 13, 2017
    Bosnia is cancelling a tender for part of its Corridor 5C project, an integral part of the class-A north-south central European route E73. Route E73 runs around 700km from Hungary south through eastern Croatia to Bosnia and Herzegovina and the Adriatic Sea in the area of Ploče port. The longest part of this corridor goes through Bosnia and Herzegovina – nearly 340km. Director of the Bosnian motorways company Autoput FBiH, Adnan Terzic, confirmed the cancelled tender to the Bosnian daily newspaper Dnev
  • Croatia’s Peljesac Bridge progressing
    June 11, 2020
    China Road and Bridge Corporation is working through the pandemic period.
  • Legal battle for Croatia’s Peljeski Bridge contract continues
    April 19, 2018
    Only days after Croatia rejected initial complaints, contractors Astaldi, Ictas and Strabag said that they will submit new complaints over the Peljeski bridge winning bid. Croatian media report that Turkey's Ictas, Italy's Astaldi and the Austrian company Strabag are planning to submit a new complaint to the Croatian High Court against a decision by the state procurement authority DKOM to reject their previous complaints. At issue is the awarding of the Peljeski bridge and access roads project to the