2010 GRAA Winner Profiles

Our series of profiles on winning projects from the 2010 Global Road Achievement (GRAA) Awards continues with the Construction Methodology Category won by Barrier Systems/Utah Department of Transportation With any major road construction project, the disruption of traffic flow is of paramount concern for engineers, workers and travellers, particularly as it relates to increased traffic delays and the safety of those driving through the work zone.
February 13, 2012 Read time: 3 mins

Our series of profiles on winning projects from the 2010 Global Road Achievement (GRAA) Awards continues with the Construction Methodology Category won by Barrier Systems/Utah Department of Transportation

With any major road construction project, the disruption of traffic flow is of paramount concern for engineers, workers and travellers, particularly as it relates to increased traffic delays and the safety of those driving through the work zone.

In the state of Utah, USA, work was recently completed on the 3500 South arterial in Salt Lake City, which was completely reconstructed by the Utah DoT (UDOT) Region 2 from the Bangerter Highway to 2700 West.

This busy corridor runs between 38,000-48,000 vehicles, and the first phase of the project called for two lanes to be open for traffic in each direction.

In order to keep traffic moving, plastic barrels were initially used to separate directional traffic and to delineate the work zone. The work zone area was confined and restricted and lacked positive protection. This created dangerous conditions as confused motorists occasionally turned into the work zone.

During the second phase of the project, therefore, Utah DOT addressed the serious twin challenges of traffic congestion caused by lane closures and the safety of drivers who were confused by changing traffic patterns.

Fortunately for UDOT, the 165 Barrier Systems Inc moveable barrier provided one solution for two problems.

"Moveable concrete barriers have historically been used only on highways and bridges. This was the first time that a moveable barrier was used on a major arterial in the US," said Chris Sanders, President of Barrier Systems. "The moveable barrier allowed two lanes to remain open in the peak direction. And we used a total of only three lanes, instead of the four lanes required when using barrels," said Sanders.

With the expanded work zone, the contractor was able to use larger, more efficient equipment, and work unimpeded for longer periods of time while the barrier was in place. This resulted in the elimination of one complete phase of construction, reducing the total number of phases from three to two.

An evaluation of the project commissioned by UDOT reported that construction was thereby completed seven months early. This resulted in major savings in time-related overheads for the contractor, and approximately US$1.4 million in user delay cost savings for the agency and the motoring public.

The UDOT report conservatively estimated the total benefits of using the reversible lane with moveable barrier at approximately US$2.4 million, with an additional accident cost saving of US$1 million, and a benefit to cost ratio of 4:1.

The report further stated that if all benefits were considered, the moveable barrier installation would have a benefit to cost ratio of greater than 10:1.

The prestigious GRAA award was presented during the IRF 2011 Annual Awards Luncheon and accepted on behalf of UDOT by Randy Park, Chief Engineer, and by Chris Sanders, President of Barrier Systems.

"Barrier Systems is very proud to have pioneered the use of our moveable barriers in such an innovative manner. The cost-savings alone demonstrate the real value of the product and its deployment, but even more satisfying than the cost and time savings is the safer road conditions we were able to offer to the drivers," said Sanders.

"Receiving this award from a global organisation like the 713 International Road Federation is a tremendous honour. The GRAA raises international awareness of how technology and innovative strategies like moveable barriers can accelerate construction, mitigate traffic congestion and improve safety for workers and motorists."

For more information on companies in this article

Related Content

  • 2010 GRAA Winner Profiles
    April 12, 2012
    Our series of profiles on winning projects from the 2010 Global Road Achievement (GRAA) Awards continues with the Construction Methodology Category won by Barrier Systems/Utah Department of Transportation With any major road construction project, the disruption of traffic flow is of paramount concern for engineers, workers and travellers, particularly as it relates to increased traffic delays and the safety of those driving through the work zone. In the state of Utah, USA, work was recently completed on
  • Safety barriers offer positive workzone protection
    February 10, 2012
    A road project in Utah has benefited from the use of effective barrier protection during construction. *Paul Grant reports An upgraded section of road from 3500 South in West Valley City, Utah, is now open to traffic. The link was completely rebuilt by Utah DoT (UDOT) from the Bangerter Highway to 2700 West, and the road carries traffic from West Valley toward downtown Salt Lake City and the University of Utah. The work added two centre lanes, which are now the first dedicated Bus Rapid Transit lanes in Uta
  • Reducing congestion while maximising safety in road construction work zones
    April 30, 2015
    Mike Dreznes, executive vice president at the International Road Federation (IRF) discusses road safety for work zone areas. Work zones around the world can create significant congestion and can cost society billions of dollars. Estimates in the United States alone include approximately 87,600 work zone crashes involving 37,500 injuries that result in 482 million lost hours, valued at approximately US$6.5 billion. When considering these numbers worldwide, it becomes clear that work zone safety and work zone
  • IRF announces 2012 GRAA Winners
    October 15, 2012
    Organisations behind the Rio de Janeiro's RJ122 project; the Kosovo Motorway project; and New York City's State-of-the-Art ITS Infrastructure Deployment Program were among the winners of the International Road Federation’s (IRF) 2012 Global Road Achievement Awards (GRAA) competition. This year's awards, whose winners were announced by IRF chairman and mayor of Riyadh, H.E Abdullah A. Al-Mogbel, honour nine projects from countries across the globe, each leading the way in innovation and excellence in its res