Skip to main content

Mersey river toll bridge gets the go ahead

Mersey Gateway backers have hailed the UK government’s decision to give the project planning approval as “fantastic news”.
February 21, 2012 Read time: 1 min
Mersey Gateway backers have hailed the UK government’s decision to give the project planning approval as “fantastic news”.

The approval gives the green light for the project team to begin the procurement process in earnest during 2011.

Centrepiece of the Gateway is a new six-lane toll bridge over the River Mersey between the towns of Runcorn and Widnes north-west England.

In addition to speeding up journey times and improving journey reliability in the region, the 1km crossing will act as a catalyst for investment and bring benefits over four times greater than the investment cost, which has been estimated at over £430 million (e267.5 million).

The existing Silver Jubilee Bridge will also be tolled as part of the project.

An estimated 4,640 new jobs will be created through direct employment, regeneration activity and inward investment.

It is anticipated that construction work will start within two years, and that the new bridge will take around three years to complete.

Related Content

  • Mersey Gateway: Consortia Talks
    April 4, 2012
    The competitive dialogue phase of the Mersey Gateway Project has begun. The project team are said to have held initial meetings with the three shortlisted bidding consortia, and will be working closely with each of them over the coming months. The aim is for each of the three bidders to submit their detailed proposals by the end of 2012, with an announcement about a preferred bidder likely to come in spring 2013. The value of the construction phase of the project, including land, is estimated at US$961milli
  • Residents near Mersey Gateway Bridge to get up to 300 free journeys a year
    December 12, 2013
    Halton Borough Council has revealed that all eligible residents within the North West England borough will receive up to 300 free journeys per year when the new Mersey Gateway Bridge between Runcorn and Widnes and the current Silver Jubilee Bridge become tolled in 2017. The scheme, expected to revitalise an area hit hard by the ongoing tough European economic climate, was approved at a full Halton Borough Council meeting last night (11 December 2013).
  • Merseylink wins US$3.12bn Mersey Gateway Project contract
    June 20, 2013
    Merseylink was today announced as the preferred bidder for the US$3.12 billion (£2bn) Mersey Gateway Project in North West England. Making the announcement together in the observatory in the Catalyst Museum in Widnes overlooking the River Mersey, Halton Borough Council and Merseylink also confirmed they have jointly identified savings amounting to “tens of millions of pounds” on the projected public sector contribution to the project budget.
  • Tenders received for Mersey Gateway project
    April 10, 2013
    Tenders have now been received for the Mersey Gateway Project from all three shortlisted bidders competing to deliver the project on behalf of Halton Borough Council. The full and final tenders were delivered to the project’s offices overlooking the River Mersey ahead of the deadline. The project team and its expert advisors will now spend the next few weeks assessing the three bids. The bidding teams have spent the last 18 months working on their plans to become Halton Borough Council’s private sector par