Tunnelling option for XCMG

XCMG’s largest tunnel machine, the XTR7/360, has gone straight from the production line to a reconstruction project in a county in Hunan Province. The project is for a tunnel with a full length of 1.2km, an excavation section width of 4.6m, and a height of 6.6m. Above the tunnel are residential buildings and pavement, buried for a depth of about 4m. These buildings have strict requirements on the disturbance on surrounding rock and noise control. The tunnel stratum is all rock roadways. The rocks are limes
May 30, 2018 Read time: 2 mins
XCMG’s largest tunnelling machine is being used on a project in Hunan Province
2490 XCMG’s largest tunnel machine, the XTR7/360, has gone straight from the production line to a reconstruction project in a county in Hunan Province.


The project is for a tunnel with a full length of 1.2km, an excavation section width of 4.6m, and a height of 6.6m. Above the tunnel are residential buildings and pavement, buried for a depth of about 4m. These buildings have strict requirements on the disturbance on surrounding rock and noise control. The tunnel stratum is all rock roadways. The rocks are limestone and granite with saturated uni-axial compressive strength of 90-110MPa, or over 110MPa partially. The project started in 2015, with the tunnel entrance and the tunnel exit commenced at the same time. The entrance was opened up with a hydraulic hammer, while drilling and blasting was used at the other end. However progress was slow and after a few months, the construction team withdrew due to low construction efficiency. Instead the team opted to utilise a tunnelling machine and selected the XTR7/360 from XCMG. This machine has a weight of 145tonnes, a cutting power of 360/280kW and can deliver cutting heights and widths of more than 7m. The machine is said to offer reliability and strong rock breaking ability. The machine can be adapted in various configurations to suit use in different stratum. It is also equipped with advanced features such as smart roll cable, sound and light alarms, soft start, and remote control.

XTR7/360 tunnel boring machine works in the full cross-section of the project. It has withstood hard rock formation and landslide since construction and shown stable performance. The tunneling efficiency has been significantly improved since its entry.

For more information on companies in this article

Related Content

  • Tough tunneling challenge in Italy
    May 25, 2016
    New levels of efficiency and sophistication are being seen in the latest earthmoving machines coming to market - Mike Woof writes. The earthmoving equipment segment accounts for one of the largest parts of the total market for construction machines. All around the world excavators and articulated dumptrucks (ADTs) can be seen operating on construction sites. With a massive array of manufacturers offering these machines, it is no surprise that the segment is hotly contested. In developed markets firms are en
  • Italy road tunnel project excavated
    July 9, 2018
    Italy’s A3 Highway is being upgraded, which will improve transport between Salerno and Calabria. Upgrading Italy’s A3 highway is of prime importance for developing the south of the country and is a project that has been prioritised for construction. The A3 Salerno-Reggio-Calabria highway is a non-toll road managed by ANAS, Italy’s state-owned company that constructs and maintains highways. The route runs a total of 443km, with the road having originally been built between 1966 and 1974. However, the origina
  • Bilbao benefits from major tunnel project
    February 10, 2012
    The northern Spanish city of Bilbao looks set to benefit from a major tunnel construction project aimed at reducing traffic congestion on its vehicle clogged streets. The city is building a new underground metro section, Line 3, which will help carry commuters to and from the city's commercial centre and help reduce vehicle journey times on the surface. This project is also making use of the latest piece of tunnelling equipment from Sandvik, the MT520 roadheader, a powerful machine designed and built at
  • Sandvik’s Turkish delight at groundbreaking tunnel vision
    May 20, 2014
    Turkey’s longest, and what will be the world’s fourth longest, highway tunnel is being built under Mount Ovit in the northeast of the country. Sandvik Construction is playing a vital role in the construction of the giant new structure, which will enable all-year-round access to what is a relatively remote and often snow-blocked part of Anatolia Having had their freedom of movement blighted for many years by wintertime snow blocking the D925 highway, along with narrower roads and passes, at Mount Ovit, resi