Work to start on Fehmarn Belt link to start in autumn

Construction of the Fehmarn Belt Fixed Link between Denmark and Germany should start this autumn for completion in 2028, according to the Danish government. Danish company Femern, which is responsible for the construction of the link, will begin negotiations with two contractor consortiums for the first of the project’s works which will start on the Danish side. A tunnel element fabrication yard and a works harbour must be built in Rødbyhavn, as well as a tunnel portal on Lolland. An autumn start wou
April 4, 2019 Read time: 2 mins
The 18km Fehmarn Belt Fixed Link to open in 2028 at a cost of €8.7 billion

Construction of the Fehmarn Belt Fixed Link between Denmark and Germany should start this autumn for completion in 2028, according to the Danish government.

Danish company 4782 Femern, which is responsible for the construction of the link,  will begin negotiations with two contractor consortiums for the first of the project’s works which will start on the Danish side. A tunnel element fabrication yard and a works harbour must be built in Rødbyhavn, as well as a tunnel portal on Lolland.

An autumn start would mean the link is opened on schedule, said Ole Birk Olesen, Denmark’s minister for transport, building and housing. This would also help to improve the possibility of securing the allocated 1116 European Union support of just under €421 million for the project which has an overall cost of around the €8.7 billion.

The Fehmarn Belt is a strait between the German island of Fehmarn and the Danish island of Lolland. The tunnel will replace a ferry service from Rødby and Puttgarden. The project’s approval process had been bogged down over environmental issues, especially within the German state of Schleswig-Holstein in which the southern end of 18km immersed tunnel will surface.

A Rambøll-Arup-TEC consultancy joint venture is engaged in a client consultancy services contract with Fmern. The joint venture has also worked on other landmark infrastructure projects, including the Øresund Tunnel in Denmark, the City Tunnel in Malmö, Sweden, the Medway Tunnel in England, as well as underground rail systems in Amsterdam and Copenhagen.

COWI is carrying out the detailed design of the tunnel (north tunnel section, south tunnel section, and ramps & portals). Meanwhile, 3392 SWECO is handling the design for the dredging and reclamation work.
 
A second framework contract, for technical support services to Femern, is being carried out by ÅF-Hansen & Henneberg.

Project information is available on the project’s official website, %$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 link-external www.femern.com false https://femern.com/en false false%>

For more information on companies in this article

Related Content

  • EU launches investigation into Fehmarn Belt financing model
    June 21, 2019
    The European Commission said it will investigate the public financing for the Fehmarn Belt link to see if it in line with state aid rules. The announcement follows the European Union General Court's annulment of a previous Commission decision approving the support. "Today's opening of such an investigation is an invitation for all stakeholders to provide their input, which will allow the Commission to adopt a new, well-informed final decision,” said Margrethe Vestager, EU Competition Commissioner.
  • Construction of Fehmarn Belt Link could start in 2019
    February 27, 2018
    Construction of a Fehmarn Belt Link could start a year from now – more than a year ahead of schedule, according to Danish media reports. The timing was put forward by Holger Schou Rasmussen, chairman of Femernbælt Development, and Kristian Pihl Lorenzen, the Liberal Party spokesman for traffic issues. They reportedly said that a pending environmental court case in Germany that has stalled approval by German authorities won’t hold up construction of the 18km crossing as much as had been feared. As late as
  • Ferry operators sink the financing plan for Fehmarn Belt link
    December 17, 2018
    The Court of Justice of the European Union has said Denmark’s state grant aid to the proposed Fehmarn Belt link is illegal under EU rules. The court noted that the European Commission approved the Fehmarn project’s financing – total cost likely around the €8.7 billion - in July 2015 without a formal procedure. Denmark is completely responsible for financing the project that will replace a ferry service. Part of the funds were to come through the European Union and its Connecting Europe Facility for tr
  • Fehmarn tunnel cleared for construction
    October 18, 2021
    The 17.6km Fehmarnbelt tunnel will be between Germany and Denmark.