Leaks hit Czech Blanka Tunnel and boost costs

Further problems have hit the Blanka Tunnel in Czech capital Prague. The link has been hit by a series of delays and is now suffering from leaks. The project is costing €1.43 billion and is due to open in May 2014. The company building the tunnel Metrostav, has stated that the leaks are likely to be temporary and should be dealt with by the time the link opens to traffic, when it will become part of the Prague ring road. Construction work started on the tunnel in 2007 but the project has faced a series of p
July 26, 2013 Read time: 2 mins
Further problems have hit the Blanka Tunnel in Czech capital Prague. The link has been hit by a series of delays and is now suffering from leaks. The project is costing €1.43 billion and is due to open in May 2014. The company building the tunnel Metrostav, has stated that the leaks are likely to be temporary and should be dealt with by the time the link opens to traffic, when it will become part of the Prague ring road. Construction work started on the tunnel in 2007 but the project has faced a series of problems, including three collapses. The original cost was estimated at around €1.025 billion, including €870 million for the construction work. However, due to the problems the link has suffered the project is expected to cost in the order of €1.42 billion. The cost of the project spiralled following the delays and was expected to hit €1.5 billion, causing some controversy, however the city authorities managed to peg the final cost at €1.42 billion.

Related Content

  • Concern is being shown over the state of Czech bridges
    August 2, 2012
    An inspection carried out by German specialists has highlighted technical issues with five bridges in the Czech city of Ostrava. The Czech Road and Motorway Headquarters (RSD) has said that a more comprehensive study will be required before the type of repairs needed can be identified and a programme of works established. There have been questions over the scope and accuracy of the one day inspection however.
  • Delays have hit the Czech Blanka Tunnel
    December 12, 2013
    Further delays are adding to the sorry tale of woe surrounding the construction of the Blanka Tunnel project in the Czech Republic. The tunnel was supposed to improve connectivity and reduce traffic congestion in Czech capital Prague. However following a series of disagreements over the work being carried out as well as the spiralling cost, financing, legal problems and various technical issues, the construction of the tunnel has finally ground to a halt. Czech construction firm Metrostav has said that it w
  • Tunnel delays in Czech link
    February 27, 2012
    Drilling work on the Blanka road tunnel in Czech capital Prague has now been completed.
  • Prague tunnel construction complete
    May 10, 2012
    Drilling work on the Blanka road tunnel in Czech capital Prague has now been completed. The new tunnel will become part of the Prague ring road once it is open to traffic. Construction commenced in 2007 but the project has faced a series of problems, including three collapses. The original cost was estimated at nearly €870 million for the construction works, €172 million for technology and €65 million for survey work. However, due to the problems the link has suffered the project is expected to cost close t