Croatia-Bosnia connection

The Svilaj Bridge connecting Croatia and the Federation of Bosnia and Herzegovina is nearly 40% complete, according to the contractors and the Croatian Motorways Directorate. Locally, the Svilaj Bridge – financially a 50-50 project between the two countries - is part of a motorway running from Beli Manastir to Osijek and on tyo Svilaj. But the route is also part of the motorway Budapest-Osijek-Sarajevo-Plocˇ which is the Pan European Corridor Vc (Corridor 5, branch c) connecting Budapest with the Adriatic.
October 2, 2018 Read time: 3 mins
Svilaj Bridge: part of Pan European Corridor Vc, Budapest to the Adriatic Sea
The Svilaj Bridge connecting Croatia and the Federation of Bosnia and Herzegovina is nearly 40% complete, according to the contractors and the Croatian Motorways Directorate.


Locally, the Svilaj Bridge – financially a 50-50 project between the two countries - is part of a motorway running from Beli Manastir to Osijek and on tyo Svilaj. But the route is also part of the motorway Budapest-Osijek-Sarajevo-Plocˇ which is the Pan European Corridor Vc (Corridor 5, branch c) connecting Budapest with the Adriatic. Traffic in this corridor - one of the most important branches of the pan-European TEN-T Network - is currently operating on the European route E73.

The Svilaj Bridge superstructure is a continuous beam over seven spans with a double composite cross section made of a steel box, a concrete deck and a bottom concrete slab. The steel box has variable height of 3,300-5,500mm.

The entire structure is a single expansion unit with expansion joints on only the abutments. The piers of the superstructure consist of one massive pier supporting two pot bearings. These bearings are all longitudinally sliding, except for the ones on pier S3.

Each of the two span sections has three 3.5m-wide traffic lanes with no emergency lane but a 0.5m-wide shoulder on both sides. There is also on both span sections a concrete monolith 0.75m-wide sidewalk.

The pier foundation method consists of placing a rectangular head beam on 24 to 36 reinforced concrete piles, depending on the pier location. The 180m-long reinforced concrete piles are 150cm in diameter.

Who’s who

Client: Hrvatske Autoceste, in Croatia, and the Ministry of Communications and Transport of Bosnia and Herzegovina, in Sarajevo
Designer: PZ, Zagreb
Engineer: Centar za organizaciju građenja, in Zagreb
Contractor: Joint Venture: Hering, based in Široki Brijeg, Bosnia and Herzegovina, and Viadukt, based in Zagreb

Excavation workers at all pier locations were operating inside a protective steel box that allowed the pumping out of water seepage. Stability of lateral sides of the steel box is ensured with steel bracing at the top and around 2m above the river bed.

Steel superstructure is dropped in place using land-based cranes and the deck slab is concreted in situ using mobile scaffoldding.

Bridge construction started in September 2016. The works on construction of piers S1, S2, S5 and S6 have been completed and so has the assembling of the steel structure in three out of seven bridge spans.

Reinforced concrete piles are now being constructed on piers S3 and S4, that are placed in the River Sava. Completion of the €22.3 million project is expected by next summer.

Key facts

The 660m Svilaj Bridge, costing €22.3 million, over the Sava River connects Croatia and Bosnia and Herzegovina. The composite steel structure and a concrete slab structure is 130m wide and consists of 6 piers. The design is of two parallel structures, one for each motorway carriage and three lanes. Design speed of the bridge is 80kph.

Related Content

  • Cengiz wins Corridor VC contract in Bosnia
    March 21, 2023
    Cengiz submitted the lowest bid in the tender which attracted three offers in the deal said to be worth around €361.8 million, according to Bosnia’s state highways agency Autoceste.
  • Croatia opens 17.5km section of Corridor 5c
    December 14, 2022
    The majority of the 5c, or Vc, route crosses Bosnia and Herzegovina and is a key priority for the European Bank for Reconstruction and Development (EBRD)
  • JP Autoceste eyes 2020 as completion date for Bosnia’s Corridor 5c
    March 3, 2016
    Around two-thirds of the Corridor 5c motorway project is expected to be completed by 2020, according to the director of the Bosnian motorways company JP Autoceste. Jasmin Buco said that 120km out of 337km of the motorway are complete. The corridor section, to connect Budapest with Ploce port in Croatia, is taking the most time. He said that the cost of the remaining part of the motorway is expected to be around €2.81 billion.
  • Despite earlier contractor issues, road projects in Bosnia are proceeding on track
    May 16, 2012
    Key road construction projects are now moving forward in Bosnia with work on-track for the Sarajevo ringroad as well as the Corridor Vc highway. Construction of a 130km section of the Corridor Vc highway should be complete by 2014 according to Bosnia's Ministry of Transport and Telecoms. Work on the first section of the Sarajevo ringroad should be completed within five months, following the signing of an agreement worth €17 million between the Austrian firm Strabag and the Bosnian company HP Investing. The